# NERC TO Exam Cheat Sheet

The numbers NERC TO candidates need cold, by exam domain, each with its standard and requirement: RTAs, IROL Tv, EEA levels, EOP-004 reports, COM-002 and more.

By ExamVanta · Updated October 31, 2026

Practicing for the NERC TO? [Take the free practice test](https://examvanta.com/exams/nerc-to/free-practice-test): 15 questions, no account needed.

The NERC Transmission Operator (TO) exam rewards knowing a few dozen numbers exactly. This sheet groups them by the six domains of NERC's [TO content outline](https://www.nerc.com/globalassets/programs/system-operator-certification--continuing-education/cert_exam_content_outline_to_june_2023.pdf), with the requirement behind each, in the versions in force on October 31, 2026. Requirements are paraphrased; the exact wording is on NERC's [US Reliability Standards](https://www.nerc.com/standards/us-reliability-standards) page and in its [Glossary of Terms](https://www.nerc.com/glossary-of-terms).

In the tables, TOP is the Transmission Operator, as the standards abbreviate it (there, "TO" means Transmission Owner). RC is the Reliability Coordinator, BA the Balancing Authority and GOP the Generator Operator.

## The exam itself

From NERC's [Program Manual V4.2](https://www.nerc.com/globalassets/programs/system-operator-certification--continuing-education/soc_program_manual_v4.2.pdf) and fee schedule:

| What | Number |
| --- | --- |
| Questions | 120: 100 scored, 20 unscored experimental |
| Time | 3 hours (90 seconds a question); allow 3.25 hours with the tutorial and nondisclosure agreement |
| Cut score | 76 of the 100 scored, since June 1, 2020 |
| Retake wait | 42 calendar days |
| Fee | $700 per attempt, usable within 365 days |

**Worked example: what 76 means.** You can't tell which are experimental. With 96 of 120 correct, even if all 24 misses were scored, 100 − 24 = 76 scored answers are right: a pass. Below 76 correct overall, you can't pass; in between, it depends where the misses fell. So 96 (80%) is the lowest total that passes wherever the misses fall. A practice score doesn't predict your result, so build a margin above that.

## Domain 1: Resource and Demand Balancing (13 scored questions)

BAL standards apply to Balancing Authorities, but the outline still tests their ideas.

| Rule | Number | Where |
| --- | --- | --- |
| Contingency Event Recovery Period | 15 minutes | Glossary; BAL-002-3 R1 |
| Contingency Reserve Restoration Period | Up to 90 minutes after the recovery period | Glossary; BAL-002-3 R3 |
| Reporting ACE beyond its BAAL | No more than 30 consecutive clock-minutes | BAL-001-2 R2 |
| CPS1 | At least 100% for each 12 consecutive calendar months | BAL-001-2 R1 |

## Domain 2: Transmission (29 scored questions)

FAC-011-4 sets what every RC's SOL methodology must contain; the TOP uses it (TOP-001-6 R25).

| Rule | Number | Where |
| --- | --- | --- |
| Flow, no Contingency | Within Normal Ratings; an Emergency Rating only if adjustments can finish within its time duration | FAC-011-4 R6.1 |
| Flow after a single Contingency | Within Emergency Ratings, never above the highest | FAC-011-4 R6.2 |
| Voltage | Normal System Voltage Limits with no Contingency (emergency limits on the same terms as ratings); emergency limits after one | FAC-011-4 R6 |
| System Voltage Limits | At or above in-service UVLS relay settings | FAC-011-4 R3 |
| Voltage schedule | A range, or a target with a tolerance band; copy to the RC and adjacent TOPs within 30 calendar days of a request | VAR-001-5 R1 |
| GOP notice to TOP | Within 30 minutes of an AVR or stabilizer status change or a reactive capability change; none if restored within 30 minutes | VAR-002-4.1 R3, R4 |
| Relay loadability | Evaluated at 0.85 per unit voltage and a 30-degree power factor angle; criterion 1: no operation at or below 150% of the highest seasonal Facility Rating (duration nearest 4 hours) | PRC-023-6 R1 (owners, not TOPs) |
| BES | Transmission Elements at 100 kV and above; generators connected at 100 kV or above over 20 MVA (unit) or 75 MVA (plant) | Glossary |

## Domain 3: Emergency Preparedness (10 scored questions)

| Rule | Number | Where |
| --- | --- | --- |
| Next-day study | An Operational Planning Analysis of SOL exceedances | TOP-002-5 R1 |
| Next-day plan | An Operating Plan for them; entities told their roles; plan given to the RC | TOP-002-5 R2, R3, R6 |
| Expected Emergency | Tell the RC, known impacted BAs and TOPs | TOP-001-6 R8 |
| Emergency plans | Reviewed by the RC, with load shed provisions and cold and extreme weather; load shed helpers notified yearly | EOP-011-4 R1, R7 |
| Geomagnetic disturbances | Operating Procedure or Process, if the TOP Area has a transformer with a high-side wye-grounded winding above 200 kV | EOP-010-1 R3 |

## Domain 4: Emergency Response (16 scored questions)

| EEA | Name | Circumstances |
| --- | --- | --- |
| 1 | All available generation resources in use | Non-firm sales curtailed; BA concerned about sustaining Contingency Reserves |
| 2 | Load management procedures in effect | Energy deficient BA still holds minimum Contingency Reserve |
| 3 | Firm Load interruption imminent or in progress | BA can't meet minimum Contingency Reserve |
| 0 | Termination | BA can meet Load and Operating Reserve requirements |

Only the RC declares an EEA, at any level and in any order; the energy deficient BA updates the RC at least hourly in EEA 2 and 3 (EOP-011-4 R6, Attachment 1).

| Rule | Number | Where |
| --- | --- | --- |
| RC passes on an Emergency notification | Within 30 minutes | EOP-011-4 R5 |
| Tool and telemetry outages | Tell the RC and known impacted entities: all planned, and unplanned of 30 minutes or more | TOP-001-6 R9 |
| Backup control center | Switch in 2 hours or less; yearly test with 2 continuous hours on backup; plan updated within 60 calendar days of a change | EOP-008-2 R1, R5, R7 |
| Restoration plan | RC approves or disapproves within 30 calendar days; revisions submitted within 90 calendar days of identifying an unplanned permanent BES change; verified every 5 years | EOP-005-3 R1, R4, R6; EOP-006-3 R5 |
| Blackstart Resources | Each tested every 3 calendar years; GOP reports a capability change within 24 hours | EOP-005-3 R7, R13 |
| Restoration training | Operators yearly; field switching personnel 2 hours every 2 calendar years | EOP-005-3 R8, R9 |

## Domain 5: Contingency Analysis and Reliability (20 scored questions)

| Rule | Number | Where |
| --- | --- | --- |
| Real-time Assessment | At least every 30 minutes | TOP-001-6 R13 |
| IROL | Never outside it longer than its Tv; every Tv 30 minutes or less | TOP-001-6 R12; Glossary |
| SOL exceedance | Initiate the Operating Plan, then tell the RC what was done | TOP-001-6 R14, R15 |
| Differing SOLs | Operate to the most limiting | TOP-001-6 R18 |
| Who sets limits | TOP sets SOLs and gives them to the RC; RC sets IROLs | FAC-014-3 R1 to R3 |
| Single Contingencies | Loss of a generator, circuit, transformer, shunt device or HVdc pole | FAC-011-4 R5 |
| Always communicated | IROL, stability limit and pre-Contingency Facility Rating exceedances; voltage below a normal minimum; post-Contingency results with a validated risk of instability, Cascading or uncontrolled separation | FAC-011-4 R7.1 |
| Communicated if not resolved in 30 minutes | Other post-Contingency rating and emergency voltage exceedances; voltage above a normal maximum | FAC-011-4 R7.2 |
| Planned manual load shed | Only after all other adjustments | FAC-011-4 R6.4 |

The RC's methodology sets each timeframe.

## Domain 6: Communications and Data (12 scored questions)

| Rule | Number | Where |
| --- | --- | --- |
| Three-part communication | Issue, repeat back (not necessarily word for word), confirm; reissue if wrong | COM-002-4 R1 |
| Burst instruction | Confirm at least one receiver got it | COM-002-4 R1 |
| Protocol review | At least every 12 calendar months | COM-002-4 R4 |
| In an Emergency | Repeat-back and confirmation required outright | COM-002-4 R5 to R7 |
| RC Operating Instructions | Follow unless physically impossible or against safety, equipment, regulatory or statutory requirements; say so if you can't | IRO-001-4 R2, R3 |
| Alternative Interpersonal Communication | Tested every calendar month; start repair within 2 hours of a failed test | COM-001-3 R9 |
| Interpersonal Communication failure of 30 minutes or more | Notify within 60 minutes of detecting it | COM-001-3 R10 |
| Data exchange redundancy | Tested every 90 calendar days; start restoring within 2 hours of a failed test | TOP-001-6 R21 |
| Event report | Later of 24 hours or the end of the next business day (4 p.m. local) | EOP-004-4 R2 |
| Cyber | Reportable Cyber Security Incident: initial notice within 1 hour of determination | CIP-008-6 R4 |

EOP-004-4 thresholds for a TOP (each "or more"): during a BES Emergency, firm load shedding of 100 MW, a 3% system-wide voltage reduction, a 10% deviation from nominal voltage on a Facility for 15 continuous minutes, or an uncontrolled loss of firm load from one incident for 15 minutes (300 MW if last year's peak demand was 3,000 MW or more, otherwise 200 MW); at any time, an island of 100 MW, 3 BES Facilities lost to one disturbance contrary to design, or 30 continuous minutes of control center evacuation or complete loss of Interpersonal and Alternative Interpersonal Communication, monitoring or control.

## Numbers that look alike

- **30 minutes:** the longest gap between Real-time Assessments, the ceiling on any Tv, the GOP's AVR notice, the outage that makes a tool or communication failure notifiable, and FAC-011-4's window before an unresolved post-Contingency exceedance is communicated.
- **2 hours:** the most a move to backup may take, but the least the backup test must run. After a failed test, it's when action must start, not finish.

Ask of any number: what starts its clock, and is it a limit or a minimum?

## Worked example: from tomorrow's study to today's alarm

An original example, not an exam question. Monday's Operational Planning Analysis shows that on Tuesday, with the Thornbury 345/138 kV transformer out for maintenance, losing a 138 kV line at the afternoon peak would load the Larkfield 138 kV line above its highest Emergency Rating.

1. **Monday:** prepare an Operating Plan (TOP-002-5 R2), such as redispatch near Larkfield arranged with the BA; tell its entities their roles (R3); send it to the RC (R6).
2. **Tuesday:** Real-time Assessments, at least every 30 minutes (TOP-001-6 R13), watch for it.
3. **If the 14:30 assessment shows it:** initiate the plan (R14) and tell the RC what you did (R15). Still unresolved at 15:00? The RC's methodology requires a report (FAC-011-4 R7.2).

Domain guides: [resource and demand balancing](https://examvanta.com/guides/nerc-to-resource-and-demand-balancing), [voltage and protection](https://examvanta.com/guides/nerc-to-voltage-reactive-and-protection), [emergency operations](https://examvanta.com/guides/nerc-to-emergency-operations-and-restoration), [contingency analysis](https://examvanta.com/guides/nerc-to-contingency-analysis-and-real-time-assessments), [SOLs and IROLs](https://examvanta.com/guides/nerc-to-sols-and-irols) and [communication and reporting](https://examvanta.com/guides/nerc-to-communications-and-reporting). Definitions: [NERC TO Glossary terms](https://examvanta.com/guides/nerc-to-glossary-terms). Then try the [free NERC TO practice test](https://examvanta.com/exams/nerc-to/free-practice-test) and full [NERC TO practice exams](https://examvanta.com/exams/nerc-to).

Free to share: you may copy and share this guide unchanged, for non-commercial purposes such as teaching and study, if you credit ExamVanta and link to this page. It's licensed under [CC BY-NC-ND 4.0](https://creativecommons.org/licenses/by-nc-nd/4.0/). Material from other sources quoted or shown in it, such as official text or chart excerpts, keeps its own terms.

Practice for the NERC TO

Start with the free practice test: 15 questions, no account needed. Every answer is explained when you finish.

[Take the free NERC TO practice test](https://examvanta.com/exams/nerc-to/free-practice-test) [See all 20 practice tests ($79)](https://examvanta.com/exams/nerc-to)

## More NERC TO guides

- [How to Prepare for the NERC TO Exam: A Study Plan by Domain](https://examvanta.com/guides/how-to-prepare-for-the-nerc-to-exam)

  An eight-week study plan for the NERC TO exam: study hours split by the weight of NERC's six domains, the standards to read, and how to use full practice exams.
- [NERC TO Certification Renewal: CEH Requirements Explained](https://examvanta.com/guides/nerc-certification-maintenance-ce-hours)

  Keeping a NERC TO credential: 140 CE hours in 3 years with 30 on standards and 30 simulation, how hours count, the $475 renewal, suspension and the new SOCCED.
- [NERC TO Exam Format, Registration and Test Day](https://examvanta.com/guides/nerc-to-exam-format-and-registration)

  How the NERC TO exam is set up and booked: 120 questions in 3 hours, SOCCED and Pearson VUE, the $700 fee, ID rules, the 42-day retake wait and renewal.
- [NERC TO Exam Glossary Terms: SOL, IROL, Emergency and More](https://examvanta.com/guides/nerc-to-glossary-terms)

  The NERC Glossary terms the TO exam turns on, paraphrased, with the detail that decides each one and the pairs people mix up: SOL vs IROL, Emergency vs EEA and more.
- [NERC TO Exam Passing Score and How Hard It Is](https://examvanta.com/guides/nerc-to-passing-score-and-difficulty)

  The NERC TO exam's cut score of 76 out of 100 scored questions, how NERC sets it, what NERC does and doesn't publish about pass rates, and what makes the exam hard.
- [NERC TO Exam: Contingency Analysis and Real-time Assessments](https://examvanta.com/guides/nerc-to-contingency-analysis-and-real-time-assessments)

  How the NERC TO exam tests contingency analysis: Real-time Assessments every 30 minutes, state estimators, bad data, acting on results and what to do when the tools fail.
- [NERC TO Exam: Emergency Operations and System Restoration](https://examvanta.com/guides/nerc-to-emergency-operations-and-restoration)

  Emergency topics on the NERC TO exam: EOP-011 plans and Energy Emergency Alerts, GMD and weather, losing the control center, and restoration from Blackstart Resources.
- [NERC TO Exam: Resource and Demand Balancing, Frequency, ACE](https://examvanta.com/guides/nerc-to-resource-and-demand-balancing)

  Resource and Demand Balancing on the NERC TO exam: frequency response, ACE and AGC, BAL-002-3 reserves, interchange and IBRs, and where a Transmission Operator fits in.
- [NERC TO Exam: SOLs and IROLs for Transmission Operators](https://examvanta.com/guides/nerc-to-sols-and-irols)

  System Operating Limits and IROLs for the NERC TO exam: the 2024 SOL definition, who sets each limit, IROL Tv, what TOP-001-6 requires in real time, with worked examples.
- [NERC TO Exam: Three-Part Communication and Reporting](https://examvanta.com/guides/nerc-to-communications-and-reporting)

  The Communications and Data domain of the NERC TO exam: COM-002 repeat-back, COM-001 communication capability, EOP-004 event reports and the notifications in TOP-001-6.
- [NERC TO Exam: Voltage, Reactive Power and Protection Basics](https://examvanta.com/guides/nerc-to-voltage-reactive-and-protection)

  The NERC TO exam's Transmission domain: reactive power and voltage control, VAR-001 and VAR-002, protection systems, RAS and relay loadability, with worked math.
- [NERC TO vs RC vs BT vs BI: The Four NERC Certification Types](https://examvanta.com/guides/nerc-certification-types-to-vs-bt-vs-rc)

  The four NERC system operator credentials compared: who RC, BT, TO and BI are for, exam size and cut score, CE hours, which desks each can staff, and how to choose.

## Sitemap

- [All exams](https://examvanta.com/exams.md)
- [Guides](https://examvanta.com/guides.md)
- [Every public page](https://examvanta.com/sitemap.md)
- [About this site for AI agents (llms.txt)](https://examvanta.com/llms.txt)