NERC TO Exam

Emergency topics on the NERC TO exam: EOP-011 plans and Energy Emergency Alerts, GMD and weather, losing the control center, and restoration from Blackstart Resources.

Practicing for the NERC TO? Take the free practice test: 15 questions, no account needed.

Two of the six domains on the NERC Transmission Operator (TO) exam are about emergencies. NERC's TO content outline gives Emergency Preparedness 10 scored questions (same-day and next-day planning 4; weather, natural disasters and geomagnetic disturbances 4; anticipated capacity deficiency 2) and Emergency Response 16 (system restoration 5, response to disturbances 4, capacity emergencies 2, loss of control center 2, loss of analysis and monitoring tools 3). Together that's a quarter of the exam.

Most of it comes from the EOP standards, read from the Transmission Operator's side. The versions below are those in force in late 2026; check NERC's US Reliability Standards page for anything newer.

What counts as an Emergency

These definitions are paraphrased from NERC's Glossary of Terms:

  • Emergency (BES Emergency): any abnormal system condition that needs automatic or immediate manual action to prevent or limit the failure of transmission facilities or generation supply that could harm the reliability of the Bulk Electric System.
  • Capacity Emergency: a Balancing Authority Area's operating capacity plus firm purchases can't meet its demand plus regulating requirements.
  • Energy Emergency: a Load-Serving Entity or Balancing Authority has used up every other resource option and can no longer meet its expected Load obligations.

Under TOP-001-6, a Transmission Operator must tell its Reliability Coordinator, known impacted Balancing Authorities and known impacted Transmission Operators about actual or expected operations that result in, or could result in, an Emergency (R8). It must also help other Transmission Operators in its Reliability Coordinator Area when asked and able, once the requester has used its own comparable Emergency procedures (R7).

Before the emergency: planning, weather and GMD

  • Next-day planning (TOP-002-5): an Operational Planning Analysis of whether next-day operations will exceed SOLs, an Operating Plan for what it finds, the roles of the entities in it, and a copy to the Reliability Coordinator.
  • Outage coordination (IRO-017-1): the Reliability Coordinator runs the outage coordination process, and the Transmission Operator does the functions it's assigned in it.
  • Geomagnetic disturbances (EOP-010-1): the Reliability Coordinator passes on forecast and current space weather information. A Transmission Operator whose area includes a power transformer with a high-side wye-grounded winding above 200 kV has a GMD Operating Procedure or Process with steps to receive that information, operator actions triggered by predetermined conditions, and the conditions for ending it.
  • Cold and extreme weather: EOP-011-4 plans must include ways to determine the reliability impacts of cold and extreme weather. A Transmission Operator's TOP-003 data specification also covers notifications of generating units' limitations in local forecast cold weather; that part dates from TOP-003-5 (April 1, 2023) and carries on in TOP-003-7. The generators' own cold weather preparations are in EOP-012-3, which applies to Generator Owners and Operators, not Transmission Operators.

During the emergency: EOP-011-4

EOP-011-4 (effective October 1, 2024) requires each Transmission Operator to develop, maintain and implement Operating Plans to mitigate operating Emergencies, reviewed by its Reliability Coordinator. They include, as applicable:

  • roles for activating the plan;
  • notifying the Reliability Coordinator, with current and projected conditions;
  • canceling or recalling transmission and generation outages;
  • reconfiguring the transmission system;
  • requesting generation redispatch;
  • operator-controlled manual load shed, undervoltage load shed (UVLS) or underfrequency load shed (UFLS), with provisions to shed fast enough, to minimize overlap between load shed circuits and circuits serving designated critical loads, to minimize overlap between manual load shed circuits and UFLS or UVLS circuits, to use UFLS or UVLS circuits for manual shedding only when warranted, and to identify and prioritize critical natural gas infrastructure loads.

When a Transmission Operator or Balancing Authority notifies the Reliability Coordinator of an Emergency, the Reliability Coordinator notifies the other Balancing Authorities and Transmission Operators in its area, and neighboring Reliability Coordinators, within 30 minutes. It also declares Energy Emergency Alerts:

Level Meaning
EEA 1 All available generation is in use
EEA 2 Load management procedures are in effect
EEA 3 Firm Load interruption is imminent or in progress
EEA 0 The alert is ended

The Reliability Coordinator can declare any level without going through them in order. EEAs belong to the Balancing Authority's energy problem, but a Transmission Operator has to know what each one means for the load it may be asked to shed.

Losing the primary control center: EOP-008-2

A Transmission Operator needs an Operating Plan for loss of its primary control center, and backup functionality staffed by certified operators. The plan has to cover the backup location and tools, data exchange, communications, power, security, who decides to move, and a transition to full backup functionality of two hours or less. Copies sit at both sites, the primary and backup can't depend on each other, the plan is reviewed every year, and an annual test has to show the transition time and at least two continuous hours of operating from the backup.

Losing analysis tools without losing the building is a separate subarea (3 questions). It's covered in NERC TO contingency analysis and Real-time Assessments.

Restoring the system: EOP-005-3 and EOP-006-3

When part of the system has shut down and Blackstart Resources are needed, the Transmission Operator restores its system under a restoration plan approved by its Reliability Coordinator (EOP-005-3 R1). The plan's job ends when the next Load to restore is no longer driven by the need to control frequency or voltage. It includes:

  • strategies coordinated with the Reliability Coordinator's high-level strategy;
  • how off-site power for nuclear plants will be provided, and its priority;
  • restoring interconnections with other Transmission Operators under the Reliability Coordinator's direction;
  • each Blackstart Resource: a generating unit that can start without support from the System (or stay energized without it), can energize a bus, meets the plan's needs for real and reactive power and frequency and voltage control, and is in the plan;
  • each Cranking Path, the part of the system that can be isolated and energized to deliver power from a generation source so other units can start, and the initial switching;
  • acceptable voltage and frequency limits during restoration;
  • processes for reconnecting restored areas, restoring the Loads needed to stabilize generation, frequency and voltage, and handing control back to the Balancing Authority.

The Reliability Coordinator leads restoration of its wider area under EOP-006-3, approves or disapproves each Transmission Operator's plan within 30 calendar days, and runs restoration drills the Transmission Operator takes part in.

Worked example: a control center evacuation

This is an original example, not an exam question.

On a Tuesday at 10:00, a fire alarm forces the operators out of the primary control center.

  • EOP-008-2: the plan's transition to full backup functionality must take two hours or less, so the backup should be fully running by 12:00 at the latest. The plan's transition-period process (who to notify, what risks to manage) applies until then.
  • EOP-004-4: an unplanned evacuation of a Transmission Operator's control center for 30 continuous minutes or more is a reportable event. At 10:30 the threshold is met. The report is due by the later of 24 hours after recognizing it (Wednesday 10:30) or the end of the next business day (Wednesday 4:00 p.m. local), so Wednesday at 4:00 p.m.
  • If the evacuation also cuts off communications or monitoring, other reporting and notification rules apply, as covered in NERC TO three-part communication and reporting.

Numbers to know

Number Rule
30 minutes Reliability Coordinator passes on an Emergency notification (EOP-011-4)
2 hours or less Transition to backup control center functionality (EOP-008-2)
2 continuous hours, annually Backup functionality test (EOP-008-2)
Annually Restoration plan reviewed and sent to the Reliability Coordinator; restoration training for System Operators (EOP-005-3)
90 calendar days Revised restoration plan after an unplanned permanent BES change (EOP-005-3)
Every 3 calendar years Each Blackstart Resource tested (EOP-005-3)
Every 5 years Restoration plan verified by analysis, simulation or testing (EOP-005-3)
2 hours every 2 calendar years Restoration training for field switching personnel (EOP-005-3)

The annual restoration training covers the plan and coordination with the Reliability Coordinator and Generator Operators, restoration priorities, building cranking paths, synchronizing re-energized sections, and handing demand and resource balance back to the Balancing Authority. Those five topics make a good checklist for this domain.

The NERC TO study plan gives emergencies weeks 4 and 5. Practice them on the free NERC TO practice test or the full NERC TO practice exams.

Free to share: you may copy and share this guide unchanged, for non-commercial purposes such as teaching and study, if you credit ExamVanta and link to this page. It's licensed under CC BY-NC-ND 4.0. Material from other sources quoted or shown in it, such as official text or chart excerpts, keeps its own terms.