NERC TO Exam

The NERC TO exam's Transmission domain: reactive power and voltage control, VAR-001 and VAR-002, protection systems, RAS and relay loadability, with worked math.

Practicing for the NERC TO? Take the free practice test: 15 questions, no account needed.

Transmission is the largest domain on the NERC Transmission Operator (TO) exam: 29 of the 100 scored questions, according to NERC's TO content outline. Its subareas are protection and control (5), voltage and reactive (5), electrical fundamentals (4), reconfiguration and switching (5), operating limits (5) and transmission equipment (5). This guide covers the physics an operator uses and the standards that turn it into duties. Operating limits have their own guide, NERC TO SOLs and IROLs.

For deeper reading, NERC's approved references include Miller and Malinowski's Power System Operation and EPRI's Power System Dynamics Tutorial, both listed in NERC's Exam Resource Materials.

Electrical fundamentals an operator uses

Four relationships cover most of the arithmetic:

  • Three-phase apparent power: MVA = √3 × line-to-line kV × kA.
  • Real power: MW = MVA × power factor.
  • Reactive power: Mvar = √(MVA² − MW²).
  • A shunt capacitor's output scales with the square of voltage: Mvar delivered = rated Mvar × (actual voltage ÷ rated voltage)².

NERC's Glossary describes Real Power as the part of electricity that supplies energy to the Load, and Reactive Power as the part that sets up and sustains the electric and magnetic fields of AC equipment. Motors and transformers need it, and it also supplies the reactive losses of transmission facilities. Generators, synchronous condensers and capacitors provide it, and it directly influences system voltage.

Worked example 1. A 345 kV line carries 1,000 A. Its apparent power is √3 × 345 × 1.0 ≈ 598 MVA. At a power factor of 0.95, that's about 568 MW.

Worked example 2. A generator delivers 100 MVA at a power factor of 0.9. Real power is 100 × 0.9 = 90 MW. Reactive power is √(100² − 90²) = √1,900 ≈ 43.6 Mvar.

Worked example 3. A 50 Mvar capacitor bank, rated at nominal voltage, is switched in while voltage is at 0.95 per unit. It delivers 50 × 0.95² ≈ 45 Mvar, not 50. That's why capacitors help least when voltage is lowest, and why a low-voltage problem can get worse quickly.

These examples are original, not exam questions.

How voltage and reactive power behave

  • Reactive power supports voltage where it's produced. Switching in a shunt capacitor raises nearby voltage; switching in a shunt reactor lowers it. Reactive power doesn't travel well over long distances, so it's best supplied close to where it's needed.
  • Line loading changes the balance. A heavily loaded line absorbs reactive power and voltage sags along it. A lightly loaded line's charging produces reactive power, which can push voltage high at night or during light load.
  • Transformer taps move voltage between sides; they don't create reactive power. Raising voltage on one side with a tap change draws the reactive power from somewhere else.
  • Generators are the largest controllable source. Their automatic voltage regulators (AVRs) hold voltage by changing reactive output within the unit's capability.

What VAR-001-5 and VAR-002-4.1 require

VAR-001-5 (effective January 1, 2019) applies to the Transmission Operator. It must:

  • specify a system voltage schedule, a range or a target with a tolerance band, as part of its plan to operate within SOLs and IROLs, and give it to its Reliability Coordinator and adjacent Transmission Operators within 30 days of a request;
  • schedule enough reactive resources to regulate voltage in normal and Contingency conditions, and operate or direct the devices that regulate voltage and reactive flow;
  • give each Generator Operator a voltage or Reactive Power schedule at the high or low side of its step-up transformer, direct it to follow the schedule with the AVR in service, and tell it when deviations must be reported.

VAR-002-4.1 applies to the generators. The Generator Operator runs in automatic voltage control unless exempted, and must tell the Transmission Operator within 30 minutes of a status change on its AVR, power system stabilizer or other voltage control device, or of a change in reactive capability. If the status is restored within those 30 minutes, no notice is needed.

Worked example 4. A Generator Operator's AVR drops to manual at 13:05. Unless it's back in automatic by 13:35, the Generator Operator must have told the Transmission Operator by 13:35. For the Transmission Operator, a unit on manual no longer regulates voltage automatically: its excitation stays where it was set, so it won't pick up reactive output to hold voltage after a disturbance, and its reactive support in the Real-time Assessment changes.

Two voltage limits from other standards come up too. The Reliability Coordinator's SOL methodology must set System Voltage Limits at or above the settings of any undervoltage load shedding relays (FAC-011-4). And under EOP-004-4, a Transmission Operator reports a system-wide voltage reduction of 3% or more, and a voltage deviation of 10% or more of nominal sustained for 15 continuous minutes during a BES Emergency.

Protection and control

Paraphrasing NERC's Glossary:

  • A Protection System is the protective relays, the communications they need, the voltage and current sensing devices feeding them, the station dc supply and the control circuitry through the breaker trip coils.
  • Normal Clearing is a protection system working as designed and clearing a fault in the time normally expected.
  • A Remedial Action Scheme (RAS) detects predetermined System conditions and automatically takes corrective action, such as adjusting or tripping generation, tripping load or reconfiguring the System, to keep the system stable, within limits and away from Cascading. The definition lists things that are not a RAS on their own, including fault-clearing protection, UFLS and UVLS schemes made only of distributed relays, out-of-step tripping, automatic reclosing, and generator controls such as AVR and governors. RAS was called Special Protection System (SPS) before April 1, 2017; the outline still writes "SPS/RAS".

What the PRC standards mean for an operator:

  • PRC-023-6, relay loadability: Transmission Owners set line relays so they don't trip on load, for example at or below 150% of the highest seasonal Facility Rating, evaluated at 0.85 per unit voltage and a 30-degree power factor angle. When an owner uses one of the practical-limit criteria instead, that calculated capability becomes the circuit's Facility Rating, and the Planning Coordinator, Transmission Operator and Reliability Coordinator have to agree to it (R3).
  • PRC-005-6, maintenance: owners maintain Protection Systems, reclosing and RAS on set intervals. The operator's part is knowing what's degraded: Real-time Assessments must reflect known Protection System and RAS status or degradation, and TOP-003-7 data specifications cover notifications of it.
  • PRC-024-4 and PRC-029-2, ride-through: generator protection must not trip units inside defined frequency and voltage "no trip zones"; inverter-based resources moved to PRC-029-2 on October 1, 2026.
  • PRC-026-2, power swings: owners check load-responsive relays on elements prone to power swings.

Worked example 5. A RAS that trips a generator after a line outage is out of service for testing. If your Real-time Assessment still counts on it, the post-Contingency results look better than they really are. The fix is the input, not the study: the assessment has to reflect the RAS's actual status, which can turn a clean result into an SOL exceedance.

Switching and equipment

Reconfiguration and switching is 5 scored questions. The Glossary's own example of an Operating Procedure, a document of specific steps to follow in order, is the list of steps for removing a specific transmission line from service. COM-002-4 requires communication protocols to name transmission interface Elements and Facilities consistently, and EOP-005-3 requires restoration training for field switching personnel who'd do unusual tasks in a restoration. Know the equipment those procedures switch: breakers, disconnects, transformers and their taps, shunt capacitors and reactors, and flow control devices such as phase-shifting transformers.

The NERC TO study plan gives this domain its first two weeks. Practice it on the free NERC TO practice test and the full NERC TO practice exams.

Watch the video lesson

Free to share: you may copy and share this guide unchanged, for non-commercial purposes such as teaching and study, if you credit ExamVanta and link to this page. It's licensed under CC BY-NC-ND 4.0. Material from other sources quoted or shown in it, such as official text or chart excerpts, keeps its own terms.